KP Energy Ltd commissions further 12.6 MW wind power project



Posted On : 2024-05-06 00:06:17( TIMEZONE : IST )

KP Energy Ltd commissions further 12.6 MW wind power project

KP Energy has successfully commissioned further 12.6MW (Phase-IX) ISTS connected Wind Power Project comprising 6 numbers of WTGs of 2.1MW each at Sidhpur site in Devbhoomi Dwarka. This Phase-IX commissioning is a part of the 250.8MW ISTS connected Wind Power Project capacity awarded to Apraava Energy Private Limited by Solar Energy Corporation of India Limited (SECI) under Tranche-VIII bidding. KP Energy is developing the Project for Apraava Energy Private Limited as a Contractor under the Land and Balance of Plant Contract.

With the present Phase-IX commissioning, the net cumulative capacity commissioned at Sidhpur site stands at 222.6MW (i.e., 52.5MW + 29.4MW + 25.2MW + 21MW+ 10.5MW + 25.2MW + 29.4MW + 16.8MW + 12.6MW) against the awarded capacity of 250.8MW.