GAIL's MNJPL project nears completion, full commissioning by 31st December 2025



Posted On : 2025-09-25 16:27:38( TIMEZONE : IST )

GAIL's MNJPL project nears completion, full commissioning by 31st December 2025

GAIL (India) Limited, India's integrated energy major, is executing Mumbai-Nagpur-Jharsuguda pipeline project (MNJPL) as part of National Gas Grid (NGG). This pipeline is categorized as high impact projects under PM GatiShakti National Master Plan initiative of Government of India. This 1,707 km natural gas pipeline project is passing through four states namely Maharashtra, Madhya Pradesh, Chhattisgarh and Odisha. This natural gas pipeline will ensure availability of clean fuel and cater to the demands of CGD and industrial sector. Petroleum and Natural Gas Regulatory Board (PNGRB) has also identified 17 Geographical Areas (GAs) covering 60 districts along this pipeline network.

As of now, pipeline construction has been completed in the state of Chhattisgarh, Odisha, and Madhya Pradesh. In Maharashtra, project execution is in its final stages and only 11 kilometres of pipeline construction is remaining out of total 1,707 km of pipeline. Further, 1,440 km of pipeline is ready for gas-in.

With construction work nearing completion in the state of Maharashtra, GAIL(India) Limited anticipates full commissioning of the MNJPL project by 31st December, 2025. The decision was approved by the GAIL's Board of Directors in a meeting held on 24th September, 2025.

Shares of GAIL (India) Limited was last trading in BSE at Rs. 175.75 as compared to the previous close of Rs. 178.70. The total number of shares traded during the day was 3741788 in over 8084 trades.

The stock hit an intraday high of Rs. 179.05 and intraday low of 175.55. The net turnover during the day was Rs. 659622946.00.