PNC Meerut Haridwar Highways Private Limited, wholly owned subsidiary of PNC Infratech Limited (the Company) has received communication from National Highways Authority of India on 11.03.2021 confirming the achievement of Financial Closure for the subject project on 10.02.2021, as detailed below:
The SPV is PNC Meerut Haridwar Highways Private Limited (Concessionaire) and project bid cost is Rs. 1412 crores.
The Construction Period is 730 days.
The Project: 53.95 km long Four-laning of Meerut - Nazibabad section of NH-119 (New NH-34) in the state of Uttar Pradesh under Bharatmala Pariyojana.
Concession Period including Construction Period: 17 years